Road Closure Update:

Installation of Sidewalk and Streetscape continue between Delaware Avenue and Franklin Street.

Allen Street is scheduled to re-open from Franklin Street to Virginia Place on May 15th.

Allen Street will remain closed from Virginia Place to Delaware Ave.

Beginning May 15th the contractor will begin reconstruction of the east side of the Allen Street / Delaware Avenue intersection. This phase of reconstruction is scheduled to be completed by mid-June, at which time the contractor will begin construction on the west side of the Allen Street / Delaware Ave intersection.

Two-way traffic on Delaware Avenue will be maintained at all times.

Landscaping is scheduled to begin the week of May 15th, from Main Street to Delaware Avenue.

The current expected Project completion is August, 2020.